Amsterdam Westpoort (AMS01)


A 78MW fully leased, six-acre site in Westpoort
Our Amsterdam data centre campus will comprise of three 85-metre towers, powered by a private substation with a firm connection into the 50kV grid. Each of the three towers will house 26MW of data halls, designed to support high density compute with high efficiency cooling achieving the Netherlands energy efficiency target PUE of 1.2. The private substation is already constructed and live, with development of the data halls from January 2026.
The entire 78MW campus is already fully leased, with Pure DC investing over €1 billion to develop the site. Development will directly provide over 1,000 jobs and support many more roles through the extended supply chain. Once complete, the data centre will provide approximately 80 permanent skilled jobs including engineers, maintenance, security and administrative staff.
At a glance
Land area:
5.68 acres
DC buildings:
3
Building size:
94,660 SQM
Status:
Sub-station operational. Data hall construction from January 2026
WUE:
N/A
PUE:
Target 1.2

+€1bn
Invested
+1,000
Jobs directly provided
78MW
Total site capacity
1.2 PUE
Target power usage effectiveness
5.68
Acres - total land area